Evolution of Six Sigma
The concept of Six Sigma evolved progressively over a period of two
decades in step with the concerns of the organizations worldwide for
quality, value-creation and customer delight. The phases of this
evolution can be identified as being concurrent with emphasis on some
of the critical business parameters. The timelines can be approximately
summarized as follows:
n
o
i
t
a
n
m
i
i
l
E
t
c
e
f
e
D
n
o
i
t
c
u
d
e
R
t
s
o
C
n
o
i
t
a
e
r
C
e
u
a
V
l
1980
1990
2000
© 2014 6sigmastudycom. All rights reserved
3
What is Six Sigma?
Six Sigma is a data driven, customer focused, and result oriented
methodology which uses statistical tools and techniques to
systematically eliminate the defects and inefficiencies to improve
processes.
Six Sigma methodology has the following characteristics:
• Customer centric
• Process focused
• Data driven/ factual
• Breakthrough performance gains
• Structured improvement deployment
• Validation through key business results
© 2014 6sigmastudycom. All rights reserved
4
Goals of Six Sigma
Reduction in variation
Elimination of defects
Improvement in yield
Enhancement in customer satisfaction
Strengthening of the bottom line
Example: GE’s Medical System division (GEMS) used Six Sigma design
techniques to create a breakthrough in medical scanning technology. Patients
can now get a full body scan in half a minute, versus three minutes or more with
Advertisement
previous technology. Hospitals can increase their usage of the equipment and
achieve a lower cost per scan, as well.
© 2014 6sigmastudycom. All rights reserved
5
Six Sigma Approach
Six Sigma approach is to find out the root causes of the problem,
symbolically represented by Y = F(X).
Here, Y represents the problem occurring due to cause (s) X.
© 2014 6sigmastudycom. All rights reserved
6
Why do Organizations Adopt Six
Sigma?
Organizations embrace the Six Sigma way as this methodology
systematically and measurably enhances the value of the organizations
by making them competitive, quality-conscious, customer-centric, and
forward-looking. Some of the benefits that the organizations derive from
the Six Sigma initiatives are:
• Waste prevention
• Defect reduction
• Cycle time reduction
• Cost savings
• Market share improvement
© 2014 6sigmastudycom. All rights reserved
7
Six Sigma – Mathematical Interpretation
Sigma, represented by the Greek alphabet ‘σ’, stands for standard deviation
from the ‘mean’. ‘Six Sigma’ represents six standard deviations from the
mean*.
• USL - Upper specification limit for a
performance standard. Any deviation above
this is a defect.
• LSL – Lower specification limit for a
performance standard. Any deviation below
this is a defect.
• Target – Ideally, this will be the middle
point between USL and LSL.
- 6σ
+ 6σ
LSL
T
USL
Mean: It is the simple average of data.
- Details will be provided in our Six Sigma Black
Standard deviation: It is a measure of variability of data.
Belt and Green Belt course.
© 2014 6sigmastudycom. All rights reserved
8
Six Sigma – Mathematical Interpretation
Process standard deviation (σ) should be so minimal that the process
performance should be able to scale up to 12σ (6 Sigma each on either
side of the origin on the X-axis) within the customer specification limits*.
- Details will be provided in our Six Sigma Black Belt and Green Belt course.
© 2014 6sigmastudycom. All rights reserved
9
Six Sigma – Mathematical Interpretation
Sigma
Level
3
4
5
Defect %
Resultant Situation for different industries
6.6807%
0.6210%
0.0233%
7 hrs of no power supply/month
15 minutes of unsafe drinking water/month
500 in-correct surgical operations/week
20,000 in-correct medical prescriptions/year
1 wrong landing of airplane/month
200 of mails lost/day
1 minute of unsafe drinking water supply every seven month
1 hour of no power supply once in 34 years
6
0.00034%
1.7 in-correct surgical operations/week
68 in-correct medical prescriptions/year
10 mails lost/month
Please note: As the sigma level increases, the defect percentage decreases, which improves the
efficiency of the process.
© 2014 6sigmastudycom. All rights reserved
10
Roles in Six Sigma Organization
Executive Leadership
Champion
Master Black Belt
Black Belt
Green Belt
Project Team
Team Member
Team Member
Team Member
© 2014 6sigmastudycom. All rights reserved
11
Advertisement
Roles in Six Sigma Organization
Executive Leadership - Executive Leadership includes project
sponsors and process owners. They create the Six Sigma vision for an
organization. They are responsible for ensuring that everyone in the
organization understands the vision and all work with unity of purpose to
realize it.
Champions - Champions are selected by Executive Leadership or
Senior Champions. They organize and direct the initiation, deployment,
and implementation of Six Sigma throughout the organization. They
ensure that Six Sigma is properly implemented in all the business
activities of the organization. Champions can be either Deployment
Champions or Project Champions.
© 2014 6sigmastudycom. All rights reserved
12
Roles in Six Sigma
Master Black Belts - Master Black Belts are in-house experts selected
by Champions. They manage project selection and human resource
training with the help of Champions. They train Black Belts and Green
Belts in Six Sigma implementation.
Black Belts - Black Belts are those who apply the tools and techniques
and knowledge of Six Sigma principles to a given project of an
organization. They are responsible for accomplishing the tasks
entrusted to them by Champions and Executive leadership. They
dedicate all of their work hours on Six Sigma implementation.
© 2014 6sigmastudycom. All rights reserved
13
Roles in Six Sigma
Green Belts - The Green Belts are those employees of an organization
who implement Six Sigma while discharging their other assigned duties.
Green Belts have fewer Six Sigma responsibilities compared to Black
Belts and Master Black Belts. They dedicate only a part of their work
hours on Six Sigma implementation.
Project Team - They are the employees who work on the Six Sigma
project. It includes the Project Manager as well. Project team members
need not be a Green Belt or Black Belt.
© 2014 6sigmastudycom. All rights reserved
14
Key Stakeholders
Customers – they are very important stakeholder whose requirements
have to be considered.
Employees – they are the people involved in the six sigma initiative in
the organization.
Suppliers - they are people who provide inputs to the process.
End users – they are people who actually use the product or service.
End users can also be customers.
© 2014 6sigmastudycom. All rights reserved
15
DMAIC Overview
DMAIC is a data-driven Six Sigma methodology for improving existing
products and processes.
The DMAIC process should be used when an existing product or
process requires improvement to meet or exceed the customer’s
requirements. This initiative should be consistent with the business
goals of the organization.
Companies using DMAIC Methodology: GE, Motorola, etc.
• GE – Reduces invoice defects and disputes by 98%, speeds up
payment, and creates better productivity.
© 2014 6sigmastudycom. All rights reserved
16
DMAIC Overview
D – DEFINE the problem
M – MEASURE the outcome (Y) to determine the current process
performance (baseline) and validate the measurement system
A – ANALYZE, identify X’s (root causes of the defects, variation
sources)
I – IMPROVE the process by eliminating the defects
C – Control X’s for sustained performance
© 2014 6sigmastudycom. All rights reserved
17
Define*
Inputs
Tools
Outputs
Need for Six
Organization
Project Charter
Sigma project
hierarchy
Established
Executive
High level process
metrics
Management
Sponsorship
maps
Problem
High level Pareto
Statement
Core team
charts
Roles and
identified
Idea generation
Advertisement
Responsibilities
and categorization
tools
*The Inputs, Tools and Outputs are covered in more detail in our Six Sigma Green Belt and Black Belt course.
© 2014 6sigmastudycom. All rights reserved
18
Measure*
Inputs
Tools
Outputs
Project Charter
Data Collection Tools
Well-defined
Roles and
and Techniques
Processes
Responsibilities
Detailed process
Baseline Process
Problem Statement
maps
Capabilities
Stakeholder
Cause and Effect
Process parameters
Requirements
Diagrams
affecting CTQ
Established metrics
Flowcharts
Cost of Poor Quality
Brainstorming
Statistical
Distributions
Probability
Gauge R&R study
(COPQ)
Measurement
Systems
*The Inputs, Tools and Outputs are covered in more detail in our Six Sigma Green Belt and Black Belt course.
© 2014 6sigmastudycom. All rights reserved
19
Analyze*
Inputs
Tools
Outputs
Well-defined
Failure Mode and
Important causes of
Processes
Effects Analysis
defects
Baseline Process
Data Analysis
Performance gaps
Capabilities
Hypothesis Testing
Special and common
Process parameters
affecting CTQ
Cost of Poor Quality
(COPQ)
Measurement
Systems
causes of variation
Costs and benefits of
proposed solutions
Points of Failure
*The Inputs, Tools and Outputs are covered in more detail in our Six Sigma Green Belt and Black Belt course.
© 2014 6sigmastudycom. All rights reserved
20
Improve*
Inputs
Tools
Outputs
Important causes of
Solutions Design
Costs and Benefits
defects
Matrix
of different solutions
Performance gaps
Design of
Process Capability of
Special and common
Experiments
proposed solutions
causes of variation
Taguchi Robustness
Selection of solutions
Costs and benefits of
concepts
for implementation
proposed solutions
Advertisement
Response Surface
Implementation Plan
Points of Failure
Methodology
*The Inputs, Tools and Outputs are covered in more detail in our Six Sigma Green Belt and Black Belt course.
© 2014 6sigmastudycom. All rights reserved
21
Control*
Inputs
Tools
Outputs
Costs and Benefits
Data Collection
Implemented
of different solutions
Methodology
Solutions
Process Capability of
Control Chart
Revised
proposed solutions
5S
Selection of solutions
Kaizen
Measurement
Systems
for implementation
Kanban
Control Plans for
Implementation Plan
Total Productive
Sustaining Benefits
Maintenance
Improved Process
Cycle Time
Reduction
Measurement
System Reanalysis
Capabilities
Lessons Learned
*The Inputs, Tools and Outputs are covered in more detail in our Six Sigma Green Belt and Black Belt course.
© 2014 6sigmastudycom. All rights reserved
22
Define Phase
The Define Phase is used to identify the areas of improvement and
define goals for the improvement activity and ensures that resources are
in place for the improvement project.
The Define Phase will focus on a customer requirement and identify
project CTQ’s (Critical to quality). A CTQ is a product or service
characteristic that satisfies a customer requirement or process
requirement
© 2014 6sigmastudycom. All rights reserved
23
Measure Phase
The Measure Phase evaluates the process to determine the current
process performance, that is, the baseline.
It uses exploratory and descriptive data analysis to help in
understanding the data. The Measure phase allows you to understand
the present condition of the process before you attempt to identify
improvements. The inputs to the measure phase are the outputs of the
Define phase
© 2014 6sigmastudycom. All rights reserved
24
Analyze Phase
The Analyze phase is used to identify few vital causes from a list of
potential causes obtained from the Measure phase, actually affecting
project outcome using six sigma methodologies. The data collected in
the Measure phase are examined to determine a prioritized list of the
sources of variation.
© 2014 6sigmastudycom. All rights reserved
25
Improve Phase
The improve phase of Six Sigma is used to improve the system to do
things better, cheaper or more rapidly by finding optimum solution for Y,
implement the new approach and validate using statistical methods. The
main objective of the improve phase is to improve the process by
eliminating defects.
© 2014 6sigmastudycom. All rights reserved
26
Control Phase
The control phase of Six Sigma is used to develop and implement
process control plan to ensure sustenance of the improved process. The
major activities in the control phase are to validate measurement
system, verify process improvement and develop control mechanism.
So far we have identified the best settings for each of the vital ‘X’. The
key now is to ensure that the X’s don’t fluctuate away from the targeted
setting. Process control is an important tool to ensure that the Six Sigma
project delivers lasting benefits.
© 2014 6sigmastudycom. All rights reserved
27