Worked solution
2021 PMP Mock Practice Tests
This article presents a set of project management questions from a 2021 PMP mock practice test, focusing on people management, leadership, communication, stakeholder engagement, and Agile methodologies. Each question is followed by a detailed worked solution explaining the reasoning process and the final answer, helping students develop the skills needed for the PMP certification exam.
Based on the document 2021 PMP Mock Practice Tests
This article was generated from the source document, then verified before publication.

Source document
Project Management, Agile Practices · PDF · 284 pages · 2021
Show document preview
This article presents a set of project management questions from a 2021 PMP mock practice test, focusing on people management, leadership, communication, stakeholder engagement, and Agile methodologies. Each question is followed by a detailed worked solution explaining the reasoning process and the final answer, helping students develop the skills needed for the PMP certification exam.
Question 1
What negotiation technique does Sam use to reach an agreement with a client who is dissatisfied and requests a project hold?
Sam’s client alleges a critical deliverable was overlooked despite prior approvals and wants to pause the project. To resolve this, Sam uses arbitration and mediation.
Arbitration and mediation are forms of negotiation techniques. Arbitration involves a third party making a binding decision, while mediation involves a third party facilitating dialogue to help parties reach agreement.
These methods are used when direct negotiation fails to produce results.
Answer: C. Arbitration and mediation as negotiation techniques
Question 2
How can a project manager increase collaboration and create a cooperative working environment within a team?
Among the options, conducting team-building workshops is a direct way to foster collaboration and cooperation by improving relationships and trust among team members.
Training on soft skills, pull-based systems, and encouraging self-development are helpful but less directly impactful on team collaboration than team-building activities.
Answer: C. Holding team-building workshops
Question 3
What leadership style is applied when a project manager encourages creativity and innovation by holding brainstorming meetings where no ideas are eliminated?
This approach empowers the team and fosters innovation, which aligns with transformational leadership.
Transactional leadership focuses on rules and rewards, interactional is a hybrid, and laissez-faire is hands-off.
Answer: C. Transformational
Question 4
What type of power is demonstrated when Zad’s superiors decide to adopt Agile practices and instruct him to prepare for the shift?
Power derived from formal position or authority is legitimate power.
Zad’s superiors’ decision carries influence because of their formal roles.
Answer: A. Legitimate
Question 5
What are the three dimensions of complexity faced by projects and programs?
Complexity arises from:
- System behavior: dynamic interactions within the environment
- Human behavior: attitudes and conduct of people involved
- Ambiguity: uncertainty about what to expect or how to interpret situations
Answer: B. System behavior, human behavior, and ambiguity
Question 6
How should Kim, managing an Agile software project, respond to a customer’s request to change a requirement after scope definition?
Agile embraces flexibility and welcomes change requests to adapt the product to evolving needs.
Blocking or avoiding changes contradict Agile principles, and taking the request to a formal change control board is more typical of predictive approaches.
Answer: B. Welcoming the change request
Question 7
What stage of team development is characterized by conflict, lack of trust, and different viewpoints, as observed by Fatima?
This description matches the storming stage, where team members experience rivalry and disagreements before norms are established.
Answer: D. Storming
Question 8
Which leadership style focuses on self-awareness, listening, coaching, and prioritizing the development and well-being of team members?
This is the servant leadership style, which emphasizes serving the team rather than controlling it.
Answer: A. Servant leadership
Question 9
How should a project manager handle an interested stakeholder with little authority?
Stakeholders with high interest but low authority should be kept informed to maintain engagement without overcommitting resources.
Answer: C. Keep informed
Question 10
What conflict resolution technique did Daren use when he met with conflicting team members and decided to outsource the disputed task?
Meeting to discuss and jointly decide on a solution is collaboration, working together to achieve a common goal.
Answer: B. Collaborating
Question 11
How does an Agile project manager improve communication in ambiguous, complex projects?
Agile emphasizes frequent communication to keep the team informed and adaptable.
Answer: C. Communicate frequently
Question 12
What should Angela do when a new team member lacks technical proficiency according to Adam, a trusted team member?
Providing training and mentoring helps improve the new member’s skills and integrates them effectively into the team.
Answer: C. Provide the new member with training and mentoring
Question 13
What assumption does the Expectancy Theory make about behavior?
Expectancy Theory assumes behavior is based on conscious choices, where effort leads to performance and valued rewards.
Answer: D. Behavior is based on conscious choices
Question 14
What conflict-resolution technique is used when a project manager documents a sponsor’s habitual lateness but does not address it?
This is withdrawal, avoiding confrontation and conflict.
Answer: D. Withdrawal
Question 15
Which stakeholder should be prioritized for engagement when two have high power but different awareness levels?
A high-power stakeholder who is unaware (Markus) poses more risk than a neutral one, so Markus should be prioritized to engage and gain support.
Answer: B. Markus
Question 16
How should Abigail address communication gaps in a geographically dispersed team after a virtual meeting?
Recording meetings and sharing them ensures all members can review discussions and reduces misunderstandings.
Answer: C. Record sessions and send the recording to all concerned team members
Question 17
What form of power does Nora possess as an experienced PMP-certified project manager respected for her knowledge?
Expert power comes from unique skills and knowledge that earn respect and influence.
Answer: B. Expert power
Question 18
What are two main aspects of self-organizing Agile teams?
- They have more freedom to decide how to work.
- They take greater responsibility for their tasks and outcomes.
Answer: B. It gives more freedom to the Agile team and C. It increases the sense of responsibility of team members
Question 19
What characterizes extrinsic motivators used to improve team morale?
Extrinsic motivators are external rewards such as money, gifts, or praise.
Answer: B. Include rewards, gifts, or money as incentives
Question 20
What is the basis for Caitlyn’s confidence that the customer will be satisfied with the nearly completed project?
Customer satisfaction depends on conformance to requirements and fitness of deliverables for use.
Answer: D. The conformance to project requirements and the fitness of the deliverables for use
Question 21
What should Kaegan do when some team members’ performance declines, endangering project progress?
Kaegan should identify causes of poor performance, gather feedback, and implement solutions accordingly.
Answer: D. Identify causes of bad performance, solicit systematic feedback and implement adequate solutions based on findings
Question 22
How should Aicha address strong stakeholder resistance despite the mayor’s agreement on a stadium project?
She should meet with concerned stakeholders to explain the project, establish ground rules, ensure involvement, and identify issues.
Answer: C. Schedule a meeting with concerned stakeholders to explain and involve them
Question 23
What does ethnocentrism mean, which Adolf learned to avoid?
Ethnocentrism is the belief that one’s own culture is superior to others.
Answer: C. The belief that your own culture is superior to others
Question 24
What phenomenon is illustrated when a CEO promotes Stephany to project manager based on her technical skills alone?
This is the Halo Effect, where a positive attribute in one area influences judgment in another.
Answer: D. Halo Effect
Question 25
Which factors are examples of Herzberg’s hygiene factors in a healthy work environment?
- Job security
- Salary
- Safe working conditions
Appreciation of work is a motivating factor, not a hygiene factor.
Answer: A. Job security, B. Salary, C. Safe working conditions
Question 26
In Agile projects, which focus is on doing the right things?
Leadership focuses on doing the right things, while management focuses on doing things right.
Answer: B. Leadership
Question 27
What communication method is considered most effective on an Agile project?
Face-to-face communication allows real-time verbal exchange and is most effective.
Answer: C. Face-to-face
Question 28
At which stage do stakeholders have the most influence over a project’s product in a predictive life cycle?
Stakeholders have the greatest influence during the initiating stages when key decisions are made.
Answer: A. Initiating stages
Question 29
What type of team works across different time zones and days to maximize project execution time?
Virtual teams are geographically dispersed and operate across time zones.
Answer: B. Virtual teams
Question 30
Who is known as the voice of the customer representing stakeholders’ interests to the Scrum Team?
The Product Owner bridges stakeholders and the Scrum Team, ensuring value delivery.
Answer: C. Product Owner
Question 31
Which are methods of receiving feedback from Agile project team members? (Select three)
- Team Evaluation
- Individual Evaluation
- Process Tailoring
Prototyping is a product feedback method, not team feedback.
Answer: A. Team Evaluation, C. Individual Evaluation, D. Process Tailoring
Question 32
Which element is NOT part of the PMI Talent Triangle™?
Communication skills, technical project management skills, business management and strategic skills, and leadership skills are included. Communication skills alone are not a separate element in the PMI Talent Triangle.
Answer: A. Communication skills
Question 33
Who assumes responsibility for the success of a project after the sponsor reassures executives?
Responsibility is shared among the project sponsor, C-level executives, and the project manager.
Answer: D. All the above
Question 34
What stakeholder management strategy should be used for a resistant key stakeholder with high authority?
Such stakeholders should be managed closely to address resistance and influence.
Answer: A. Manage closely
Question 35
What should a sponsor initially do to support an Agile project?
The sponsor should determine project priorities and product features.
Answer: A. Determine project priorities and product features
Question 36
How should a project manager maintain and improve stakeholder relationships?
Interactive communication, which involves two-way dialogue, is key to positive relationships.
Answer: A. Interactive communication
Question 37
What are elements that interfere with message transmission and understanding called?
These are called noise, which disrupts communication.
Answer: B. Noise
Question 38
What type of risk response is agreeing to stop construction during hurricane season?
This is avoidance, eliminating the risk by not performing work during the risky period.
Answer: D. Avoid
Question 39
How is leadership defined in the context of project success?
Leadership involves the knowledge, skills, and behaviors to guide, motivate, and direct a team to achieve organizational goals.
Answer: A. The knowledge, skills, and behaviors needed to guide, motivate and direct a team to help an organization achieve its business goals
Question 40
What is a key benefit of virtual teams in a high-tech project?
Virtual teams widen the potential resource pool by enabling access to talent worldwide.
Answer: A. Widens the potential resource pool
Question 41
Which of the following are forms of power used by project managers to influence personnel? (Select three)
- Relational power
- Situational power
- Coercive power
Seeking consensus is a technique, not a form of power.
Answer: A. Relational, B. Situational, C. Coercive
Question 42
What term describes individual differences in characteristic patterns of thinking, feeling, and behaving?
This is personality, which influences how team members interact and perform.
Answer: B. Personality
Method
This paper rewards a clear understanding of project management concepts, especially in people and communication domains, Agile principles, leadership styles, stakeholder engagement, and conflict resolution techniques. It values precise application of terminology and situational judgment aligned with PMI standards.
Successful answers demonstrate reasoning through definitions, principles, and situational analysis rather than guesswork. The exam penalizes confusion between similar concepts (e.g., types of power, leadership styles) and failure to apply Agile versus predictive approaches appropriately.
Students should carefully distinguish between negotiation, communication, and influencing techniques, and recognize the appropriate stakeholder management strategies based on power and interest. Understanding team development stages and motivational theories is essential.
Finally, the exam rewards familiarity with PMI frameworks such as the Talent Triangle and the Expectancy Theory, and the ability to identify correct responses from multiple plausible options.